Any impact of changing SQL Server log shipping restore job schedule - sql-server

On the SQL Server log shipping secondary database server, I have 2 jobs LS_Copy and LS_Restore.
Current schedule: both jobs run every 30 minutes (all day)
New schedule: I want to change the restore job to run every 30 minutes between 10:00 AM to 7:00 PM and 6:30 AM to 7:30 AM. It won't be running for the remainder of the day.
The copy job will still have the same schedule, i.e., every 30 minutes (all day)
Question: do you know if making this change can create issues I am unaware of?

I modified the schedule to new one, everything is working fine. The copy job piles up the files and whenever restore executes, it processes all the queued files in correct order.

Related

SQL Server - job history for sql job running less than 15 seconds

I am trying to figure out the issue.
we have a couple of sql job agents that runs less than 15 seconds everyday to execute store procedures.
Whenever I tried to see the job history, there is no information about it and it shows "never executed"
I did a simple test and tried to let it run say more than 60 seconds. I see it appears on the job history.
Is there any settings that I need to set so that I could see the jobs in job history that runs less than 15 seconds.
Thanks.

Disable SQL Server Agent Job temporarily

My SQL Server Agent job runs everyday 7 PM. How can I disable it to not run every 10th, 11th and 12th date of the month?
Now every month, On 9th, after completion of the job, I do manually by changing start date of the schedule to 13th. Is there any better approach get rid of this manual activity?

SQL Server agent job recreated

I stuck in a issue from last 6 months. I had a SQL Servre job SALES lOAD which is created with a T-SQL script. This job is being recreated every month automatically. How we know which job affected or recreated my SALES lOAD load every month. I checked each and every job but no job is affecting this job
You may check if there is any process scheduled to run every month (BAT file,Task scheduler job, etc...)

Transactional replication failing

i am facing issue in sql server Transactional replication and not able to get the root cause for it. First, let me tell you that i am not a DBA, so i may be dumb on few DBA concepts.
i am .Net developer and i have been given responsibility to setup the replication.
i have a Database in Headoffice and replicating few Tables to another server at retail Store.
First time, i configured the replication with selected articles.
the replication was continuous. it was running fine, but one Sunday night, it got failed with error "process could not execute 'sp_replcmds'".
after spending sometime on google, i couldn't find any solution. so, i rebuilt the Replication, but this time the replication was scheduled (every 15 Min), also i configured it as PULL instead of PUSH. it started, but again next Sunday night it got crashed.
So, i analyzed that in Sunday night, i had configured the Reindexing Job on the database, and Since, the recovery model was full, it was generating a very large TLOG and Repolication agent was not able to parse that.
Now, the third time, i again Rebuilt the Replication, and this time i scheduled the replication every 15 minutes but from 8:00 AM Morning to 11:30 PM, because after 11:30, no store do any transaction. Also, for Reindexing Job, i added 2 more steps. before Re-Indexing, i was changing the recovery model to simple and then Re-Indexing and after that i was changing the Recovery model back to Full. i was changing the recovery to Full, irrespective of the result from Re-Indexing step.
This setup was working fine and worked properly for around 2 Months.
Now, after 2 Months, again one Sunday night it got failed, with the same reason ("process could not execute 'sp_replcmds'"). Actually, i had scheduled the backup job, and i was taking Full Backup everyday and Log backup every 15 minutes, and no differential backup.
after, discovering that i had not configured the differential backup, i also configured the same (every 6 Hours). but, after configuring the Differential backup, in Sunday night Replication got failed.
Now, anybody, please help me with the recommended setup for my scenario.
my setup is
sql server - SQL Server 2008 R2 Enterprise on Windows Server 2008 R2
Distributor and Publisher are on same machine.
Subsriber is on the Retail Store server.
sp_replcmds is run by the log reader agent against the published database to get, well, replicated commands. According to the documentation, one needs to be at least db_owner to run that command. Make sure whatever account is running the log reader agent has at least db_owner in the published database.

Offsetting the start time of SQL Server Agent job schedules between instances

I have an agent job set to run log backups every two hours from 2:00 AM to 11:59 PM (leaving a window for running a full or differential backup). A similar job is set up in every one of my 50 or so instances. I may be adding several hundred instances over time (we host SQL Servers for some of our customers). They all backup to the same SAN disk volume. This is causing latency issues and otherwise impacting performance.
I'd like to offset the job run times on each instance by 5 minutes, so that instance one would run the job at 2:00, 4:00, etc., instance two would run it at 2:05, 4:05, etc., instance three would run it at 2:10, 4:10, etc. and so on. If I offset the start time for the job on each instance (2:00 for instance one, 2:05 for instance two, 2:10 for instance three, etc.), can I reasonably expect that I will get my desired result of not having all the instances run the job at the same time?
If this is the same conversation we just had on twitter: when you tell SQL Server Agent to run every n minutes or every n hours, the next run is based on the start time, not the finish time. So if you set a job on instance 1 to run at 2:00 and run every 2 hours, the 2nd run will run at 4:00, whether the first run took 1 minute, 12 minutes, 45 minutes, etc.
There are some caveats:
there can be minor delays due to internal agent synchronization, but I've never seen this off by more than a few seconds
if the first run at 2:00 takes more than 2 hours (but less than 4 hours), the next time the job runs will be at 6:00 (the 4:00 run is skipped, it doesn't run at 4:10 or 4:20 to "catch up")
There was another suggestion to add a WAITFOR to offset the start time (and we should discard random WAITFOR, because that is probably not what you want - random <> unique). If you want to hard-code a different delay on each instance (1 minute, 2 minutes, etc.) then it is much more straightforward to do that with a schedule than by adding steps to all of your jobs. IMHO.
Perhaps you could setup a centralized DB that manages the "schedule" and have the jobs add/update a row when they run. This way each subsequent server can start the job that "polls" when it can start. This way any latency in the jobs will cause the others to wait so you don't have a disparity in your timings when one of the servers is thrown off.
Being a little paranoid I'd add a catchall scenario that says after "x" minutes of waiting proceed anyway so that a delay doesn't cascade far enough that the jobs don't run.