I have a list of tasks that have dependencies between them and I was considering how I could use JGraphT to manage the ordering of the tasks. I would set up the graph as a directed graph and remove vertices as I processed them (or should I mask them?). I could use TopologicalOrderIterator if I were only going to execute one task at a time but I'm hoping to parallelize the tasks. I could get TopologicalOrderIterator and check Graphs.vertexHasPredecessors until I find as many as I want to execute as once but ideally, there would be something like Graphs.getVerticesWithNoPredecessors. I see that Netflix provides a utility to get leaf vertices, so I could reverse the graph and use that, but it's probably not worth it. Can anyone point me to a better way? Thanks!

A topological order may not necessary be what you want. Here's an example why not. Given the following topological ordering of tasks: [1,2,3,4], and the arcs (1,3), (2,3). That is, task 1 needs to be completed before task 3, similar for 2 and 4. Let's also assume that task 1 takes a really long time to complete. So we can start processing tasks 1, and 2 in parallel, but you cannot start 3 before 1 completes. Even though task 2 completes, we cannot start task 4 because task 3 is the next task in our ordering and this task is being blocked by 1.
Here's what you could do. Create an array dep[] which tracks the number of unfulfilled dependencies per task. So dep[i]==0 means that all dependencies for task i have been fulfilled, meaning that we can now perform task i. If dep[i]>0, we cannot perform task i yet. Lets assume that there is a task j which needs to be performed prior to task i. As soon as we complete task j, we can decrement the number of unfulfilled dependencies of task i, i.e: dep[i]=dep[i]-1. Again, if dep[i]==0, we are now ready to process task i.
So in short, the algorithm in pseudocode would look like this:
Initialize dep[] array.
Start processing in parallel all tasks i with dep[i]==0
if a task i completes, decrement dep[j] for all tasks j which depend on i. If task j has dep[j]==0, start processing it.
You could certainly use a Directed Graph to model the dependencies. Each time you complete a task, you could simply iterate over the outgoing neighbors (in jgrapht use the successorsOf(vertex) function). The DAG can also simply be used to check feasibility: if the graph contains a cycle, you have a problem in your dependencies. However, if you don't need this heavy machinery, I would simply create a 2-dimensional array where for each task i you store the tasks that are dependent on i.
The resulting algorithm runs in O(n+m) time, where n is the number of tasks and m the number of arcs (dependencies). So this is very efficient.

Related

Does Flink's windowing operation process elements at the end of window or does it do a rolling processing?

I am having some trouble understanding the way windowing is implemented internally in Flink and could not find any article which explain this in depth. In my mind, there are two ways this can be done. Consider a simple window wordcount code as below
env.socketTextStream("localhost", 9999)
.flatMap(new Splitter())
.groupBy(0)
.window(Time.of(500, TimeUnit.SECONDS)).sum(1)
Method 1: Store all events for 500 seconds and at the end of the window, process all of them by applying the sum operation on the stored events.
Method 2: We use a counter to store a rolling sum for every window. As each event in a window comes, we do not store the individual events but keep adding 1 to previously stored counter and output the result at the end of the window.
Could someone kindly help to understand which of the above methods (or maybe a different approach) is used by Flink in reality. The reason is, there are pros and cons to both approach and is important to understand in order configure the resources for the cluster correctly.
eg: The Method 1 seems very close to batch processing and might potentially have issues related to spike in processing at every 500 sec interval while sitting idle otherwise etc while Method2 would need to maintain a common counter between all task managers.
sum is a reducing function as mentioned here(https://nightlies.apache.org/flink/flink-docs-master/docs/dev/datastream/operators/windows/#reducefunction). Internally, Flink will apply reduce function to each input element, and simply save the reduced result in ReduceState.
For other windows functions, like windows.apply(WindowFunction). There is no aggregation so all input elements will be saved in the ListState.
This document(https://nightlies.apache.org/flink/flink-docs-master/docs/dev/datastream/operators/windows/#window-functions) about windows stream mentions about how the internal elements are handled in Flink.

what does worst case big omega(n) means?

If Big-Omega is the lower bound then what does it mean to have a worst case time complexity of Big-Omega(n).
From the book "data structures and algorithms with python" by Michael T. Goodrich:
consider a dynamic array that doubles it size when the element reaches its capacity.
this is from the book:
"we fully explored the append method. In the worst case, it requires
Ω(n) time because the underlying array is resized, but it uses O(1)time in the amortized sense"
The parameterized version, pop(k), removes the element that is at index k < n
of a list, shifting all subsequent elements leftward to fill the gap that results from
the removal. The efficiency of this operation is O(n−k), as the amount of shifting
depends upon the choice of index k. Note well that this
implies that pop(0) is the most expensive call, using Ω(n) time.
how is "Ω(n)" describes the most expensive time?
The number inside the parenthesis is the number of operations you must do to actually carry out the operation, always expressed as a function of the number of items you are dealing with. You never worry about just how hard those operations are, only the total number of them.
If the array is full and has to be resized you need to copy all the elements into the new array. One operation per item in the array, thus an O(n) runtime. However, most of the time you just do one operation for an O(1) runtime.
Common values are:
O(1): One operation only, such as adding it to the list when the list isn't full.
O(log n): This typically occurs when you have a binary search or the like to find your target. Note that the base of the log isn't specified as the difference is just a constant and you always ignore constants.
O(n): One operation per item in your dataset. For example, unsorted search.
O(n log n): Commonly seen in good sort routines where you have to process every item but can divide and conquer as you go.
O(n^2): Usually encountered when you must consider every interaction of two items in your dataset and have no way to organize it. For example a routine I wrote long ago to find near-duplicate pictures. (Exact duplicates would be handled by making a dictionary of hashes and testing whether the hash existed and thus be O(n)--the two passes is a constant and discarded, you wouldn't say O(2n).)
O(n^3): By the time you're getting this high you consider it very carefully. Now you're looking at three-way interactions of items in your dataset.
Higher orders can exist but you need to consider carefully what's it's going to do. I have shipped production code that was O(n^8) but with very heavy pruning of paths and even then it took 12 hours to run. Had the nature of the data not been conductive to such pruning I wouldn't have written it at all--the code would still be running.
You will occasionally encounter even nastier stuff which needs careful consideration of whether it's going to be tolerable or not. For large datasets they're impossible:
O(2^n): Real world example: Attempting to prune paths so as to retain a minimum spanning tree--I computed all possible trees and kept the cheapest. Several experiments showed n never going above 10, I thought I was ok--until a different seed produced n = 22. I rewrote the routine for not-always-perfect answer that was O(n^2) instead.
O(n!): I don't know any examples. It blows up horribly fast.

Starvation of one of 2 streams in ConnectedStreams

Background
We have 2 streams, let's call them A and B.
They produce elements a and b respectively.
Stream A produces elements at a slow rate (one every minute).
Stream B receives a single element once every 2 weeks. It uses a flatMap function which receives this element and generates ~2 million b elements in a loop:
(Java)
for (BElement value : valuesList) {
out.collect(updatedTileMapVersion);
}
The valueList here contains ~2 million b elements
We connect those streams (A and B) using connect, key by some key and perform another flatMap on the connected stream:
streamA.connect(streamB).keyBy(AClass::someKey, BClass::someKey).flatMap(processConnectedStreams)
Each of the b elements has a different key, meaning there are ~2 million keys coming from the B stream.
The Problem
What we see is starvation. Even though there are a elements ready to be processed they are not processed in the processConnectedStreams.
Our tries to solve the issue
We tried to throttle stream B to 10 elements in a 1 second by performing a Thread.sleep() every 10 elements:
long totalSent = 0;
for (BElement value : valuesList) {
totalSent++;
out.collect(updatedTileMapVersion);
if (totalSent % 10 == 0) {
Thread.sleep(1000)
}
}
The processConnectedStreams is simulated to take 1 second with another Thread.sleep() and we have tried it with:
* Setting parallelism of 10 to all the pipeline - didn't work
* Setting parallelism of 15 to all the pipeline - did work
The question
We don't want to use all these resources since stream B is activated very rarely and for stream A elements having high parallelism is an overkill.
Is it possible to solve it without setting the parallelism to more than the number of b elements we send every second?
It would be useful if you shared the complete workflow topology. For example, you don't mention doing any keying or random partitioning of the data. If that's really the case, then Flink is going to pipeline multiple operations in one task, which can (depending on the topology) lead to the problem you're seeing.
If that's the case, then forcing partitioning prior to the processConnectedStreams can help, as then that operation will be reading from network buffers.

runtime scheduling abstraction

I am asked to write a program,an abstraction of runtime scheduling algorithms in C.The one I'm having problem with is "priority scheduling".It takes runtimes from the user like the other algorithms,except it also takes priorities of these processes.What troubles me is that I can't relate priorities with runtimes. How am I supposed to make a relationship between the priority and the runtime?According to algorithm,it runs the one with highest priority first.I just need to know how to make this connection,thanks.
EDIT :-
Store the priorities in an array and sort out the array as per decreasing priorities and map each priority with it's timing! Then,simply display the sorted array from starting and it's mapping with the process-time.
If the process are added at run-time, the you need to adopt greedy-algorithm to solve that problem. Select that process with highest priority in increasing order of incoming time.
Check this to learn more Interval Scheduling Algorithm
BTW,for implementing the real-scheduling algorithm :-
If the first process is currently running and then there comes a new process with the same or lesser priority level, then you should add just the new process to the FIFO data-structure(queue) so that it gets executed at the next(for equal/lesser priority).
If the first process is currently running, and a new process with a higher priority arrives and requests memory, you must pass the current process' upcoming instruction to the stack and execute the higher priority process and then return interrupt to execute the upcoming instruction!
I hope you are getting confused with the DATA-STRUCTURES to implement in a peculiar manner. Also,there is significant use of priority(higher)!

Evenly distribute scent in a collaborative diffusion matrix

I am trying to implement a collaborative diffusion behaviour for the first time and I am stuck with a problem. I understand how to make obstacles not diffusing scents and how to dampen scent for other friendly agents if one of them already pursues it. What I cannot understand is how do I make scents to evenly distribute in the matrix. It seems to me that every way of iterating in the matrix, determines the scent to distribute faster and better in the tiles I check later in the iteration. I mean if I iterate from i to maxRows and j to maxCols and then I apply the diffusion equation in every tile, on the 'north' and 'west' side of the goal I will have only one tile with the correct potential, whereas in the 'east' and 'south' side I will have more of them since their neighbours already have an assigned potential. How can I make the values distribute evenly? A double iteration from both extremities of the matrix and them combining the result seems like a memory-eater, as do a goal-oriented approach, since if I try to start from the goals and work around them I will have to execute the calculations for every goal and every tile with assigned potential, which means that I will have to do it for 4^(turn since starter diffusion)*nrOfGoals more every turn, which seems inefficient in a large matrix with a lot of goals.
My question is how can I evenly distribute the values in the matrix in an efficient way. I'm using the AiChallenge Ants, if that helps in any way!
I thank you in anticipation and I'm sorry for the grammar mistakes I've made in this post.
There may be a better solution, but the easiest way to do it is to use something similar to how a simple implementation of the game of life is done.
You have two buffers. One has the current "generation" of scent (and if you are doing multitasking, can be locked so only readers can look at it)... and another has the next generation of sent being calculated. You only "mix" scents from the current generation.
Once you are done, you swap the two buffers by simply changing the pointers / references.
Another way to think about it would be to have all the tiles calculate their new sent by asking their neighbors and averaging. When asked by their neighbors what their scent level is, they report their pre-calculated values from the previous pass. The new sent is only locked in once everyone has finished calculating.

Resources